Web Design

How Long Does a Website Redesign Take? Published Ranges, Where the Weeks Go and a Date Planner

Studios publish answers from two weeks to more than a year, so a single number is no use. This guide lays the published ranges side by side, shows what actually stretches a project, and gives you a way to work backwards from the date you need to be live. Ranges read October 2026.

How Long Does a Website Redesign Take? Published Ranges, Where the Weeks Go and a Date Planner

Key takeaways

  • For a small business marketing site, most studios publish somewhere between 4 and 16 weeks. Larger and more complex sites run months, and enterprise projects run a year or more.
  • Page count is a weak predictor. The studios we read say the weeks go to decisions, reviews and content, not to design or build.
  • Add time before the work starts. Clique Studios says to plan two to four weeks between signing the contract and kickoff.
  • Slow feedback costs more than slow design. Five review points at three days each wait 15 days in total. At ten days each, they wait 50, which adds five weeks.
  • Work backwards from your launch date. Put the build, a buffer and the pre-kickoff gap on the calendar first, and the date you must sign falls out.
  • Do not shorten by skipping the groundwork. Skipping discovery, staging checks or the redirect map saves days and tends to cost weeks.

What studios publish

We read these pages in October 2026. The ranges come from different kinds of studio and different kinds of project, so treat them as a spread, not a standard.

SourceProject typePublished rangeDate of page
SkydeaVisual refresh2 to 4 weeks17 Aug 2026
SkydeaNormal marketing site8 to 12 weeks17 Aug 2026
SkydeaComplex site4 to 6 months17 Aug 2026
CubertoFocused visual refresh4 to 6 weeks26 Aug 2026
CubertoSmall custom marketing site1.5 to 2 months26 Aug 2026
CubertoCorporate or SaaS redesign2 to 3 months26 Aug 2026
AlkaliEstablished B2B site, content written by the studio6 to 8 weeks2 Sep 2026
Sharp Guys Web DesignMost business websites8 to 14 weeks27 Mar 2026
MillerMedia7Small, straightforward site4 to 6 weeks14 Nov 2025
MillerMedia7Full redesign8 to 16 weeks14 Nov 2025
Clique StudiosSmall business, 10 to 20 pages8 to 12 weeksPage read Oct 2026
Clique StudiosMid-sized, 30 to 75 pages12 to 16 weeksPage read Oct 2026
Clique StudiosLarge, 100 or more pages16 to 24 weeksPage read Oct 2026
Three Seven MarketingAll phases added up15 to 38 weeks21 Apr 2025

The Three Seven row is our arithmetic on its published phases: discovery 1 to 4 weeks, strategy 2 to 8, UX design 4 to 8, development 4 to 10, build-out 2 to 4, and quality assurance 2 to 4.

Our own published build times

At Amariq, we publish build times on our service pages, counted from an approved design:

WorkTypical time
Landing page2 to 3 weeks
Marketing website3 to 6 weeks
CMS-driven site or platform6 to 8 weeks
Webflow build3 to 6 weeks
WordPress build4 to 8 weeks
Shopify theme build3 to 7 weeks
Ecommerce build5 to 10 weeks
Focused Framer marketing site2 to 5 weeks

Two things explain why our figures sit at the low end of the table. They count from an approved design, so the discovery and design stages come before them, and they cover a focused site, not a large or complex one. Milestones and a delivery date are agreed before work starts.

Why the ranges are so wide

Four things move the number far more than the page count:

  1. How much has to change. A visual refresh on the same structure is quick. A new positioning, a new structure and a new platform are not. Cuberto makes this point: the difference usually has less to do with the number of pages than with what actually needs to change.
  2. Whether the content exists. Alkali says the projects that stretch to four and five months are almost never stuck in design or development. They are waiting on words.
  3. How fast decisions are made. Skydea says that reviews are what make projects slow, and that in larger companies work going up the chain and back down routinely takes weeks per pass.
  4. How much is migration. The redirect map, the URL inventory and the content moves are often not planned in week one. Our website redesign SEO checklist lists them.

Where the weeks go

Studios divide the work differently, but the shape is similar. As one example, Alkali describes an eight week B2B project this way: weeks one and two for diagnosis and positioning, weeks three to five for content and design done together, and weeks six to eight for build, migration and launch. Clique Studios lists discovery and strategy at two to three weeks for a mid-sized site, then information architecture and sitemap, design, development, content and testing.

A plain version for a small business site:

StageWhat happensWho holds it up
DiscoveryGoals, audience, structureYou, if the goals are not settled
DesignLayouts and visuals, reviewed and approvedReview turnaround
ContentWords, photos and proofMostly you
BuildThe site on the platform, with the CMS and formsThe studio
TestingPhones, speed, forms, redirectsThe studio, and you for sign-off
LaunchSwitch the addresses, check, monitorBoth

What it asks of your time

A redesign takes your time as well as the studio's. Clique Studios estimates 10 to 15 hours in total for the project sponsor, and 15 to 25 hours for subject matter experts, spread across kickoff, strategy review, design approvals, feedback and testing. A small business has fewer people, and the sponsor and the expert are often the same person, so plan for the upper end of the sponsor figure and a regular weekly slot.

The review wait: why feedback speed matters

Reviews are the part of the schedule you control. Suppose a project has five review points, such as the structure, two design rounds, the build and the final check:

Your turnaround per reviewTotal waiting across five reviews
3 days15 days
5 days25 days
10 days50 days

The difference between three days and ten is 35 days, which is five weeks. Nothing in the studio's plan changed. Name one decision-maker, book the review slots in the calendar at kickoff, and send consolidated feedback once, not in pieces.

A date planner that works backwards

Start from the day you need to be live and subtract:

  1. A buffer. One week is a sensible minimum, for content that arrives late or a fix found in testing.
  2. The build and testing time from the studio's plan.
  3. The pre-kickoff gap. Clique Studios says to plan two to four weeks between signing and kickoff, for contracts, the deposit and scheduling the team.

A worked example, using the upper end of our published range for a marketing website. To launch on Tuesday 2 February 2027, subtract one week of buffer, six weeks of build and two weeks before kickoff. That is nine weeks, so the contract should be signed by Tuesday 1 December 2026. With a four-week pre-kickoff gap, it is Tuesday 17 November 2026. Remember that the design and content stages come before the build, so for a project that starts from the brief, move the signing date earlier by their length.

How to shorten a redesign safely

SafeWhy it works
Have the copy and images ready before the project startsContent is the most common wait
Name one decision-makerChained approvals add weeks
Run design and content strategy at the same timePages are written and designed as pages
Cut the scope to the essential pages firstClique describes a rapid-impact scope of 6 to 10 weeks
Launch in phases when the site is largeThe first phase goes live sooner
UnsafeWhat it costs
Skipping discoveryAlkali says compressing it is the single most reliable way to make a project late, because each unresolved question becomes a revision round later
Skipping staging testsBugs reach real visitors
Skipping the redirect mapSearch traffic can fall after launch
Adding scope mid-projectEvery addition moves the date

One example of phasing

Our MyEventWiFi build ran in three stages between July and September 2026: the nine-page site first, then payments inside the booking forms, then a three-path onboarding wizard. The payment forms have taken real payments since July, and the wizard went live in September. Phasing meant the client could approve and use each piece before the next began.

How we plan a redesign

For a product company, our five-page SaaS website structure shows which pages to build first.

At Amariq, the first call is about your goals and what is holding the site back, and the proposal that follows sets milestones and a delivery date before work starts. You work directly with the senior designer and developer on your project. Our conversion-focused redesign starts with positioning and structure, and our Webflow migration page covers moves between platforms. If you are not sure the site needs a rebuild, start with the signs a website needs a redesign, and if you are comparing studios, our guide to choosing a web design agency has the questions to ask about timelines.

Frequently asked questions

How long does a website redesign take?

For a small business marketing site, studios publish roughly 4 to 16 weeks, with 8 to 12 weeks the most common answer. Refreshes are quicker and complex or large sites take months. The biggest factors are how much changes, whether the content is ready and how fast you give feedback.

How long does a small business website redesign take?

Clique Studios publishes 8 to 12 weeks for 10 to 20 pages, and Sharp Guys 8 to 14 weeks for most business websites. Our own build times are 3 to 6 weeks for a marketing website, counted from an approved design, with the discovery and design stages before that.

Why do redesigns take longer than quoted?

Usually because of waiting, not working. Skydea says reviews make projects slow, Alkali says projects stretch while waiting for content, and Skydea says chained approvals can take weeks per pass. Unplanned migration work, such as the redirect map, adds more.

Can a website redesign be done in two weeks?

A visual refresh on the same structure can be, and Skydea publishes 2 to 4 weeks for that. A full redesign with new structure, content and testing rarely can. Skipping discovery, testing or redirects to hit two weeks tends to cost more time later.

How long before the project starts should I sign?

Plan two to four weeks between signing and kickoff, according to Clique Studios, for contracts, the deposit and scheduling the team. Add the design and content stages if the project starts from a brief.

How much of my time does a redesign take?

Clique Studios estimates 10 to 15 hours in total for the project sponsor and 15 to 25 hours for subject matter experts. In a small business one person often fills both roles, so block a weekly review slot from kickoff.

When should I start if I have a launch date?

Work backwards: subtract a week of buffer, the studio's build and testing time, and a two to four week gap before kickoff. For a six week build, a week of buffer and a 2 February 2027 launch, that means signing by 1 December 2026 with a two-week gap.

Does the platform change how long it takes?

It can. Our published build times from an approved design are 3 to 6 weeks on Webflow, 4 to 8 on WordPress, 3 to 7 for a Shopify theme, 5 to 10 for ecommerce and 2 to 5 for a focused Framer marketing site. Scope and content readiness matter more than the platform.

Rahat Khondokar, founder of Amariq

Rahat Khondokar

Founder & CEO, Amariq

Rahat designs and builds websites for marketing teams and ecommerce brands, and writes here about the structure, copy and conversion work behind them. More about Amariq. Find him on YouTube, Dribbble and LinkedIn.

Keep reading

Related articles.

All articles